News and Blog
20
Nov
FY 2016
July, 2015
August, 2015
September, 2015
October, 2015
November, 2015
December, 2015
January 26, 2016
February 25, 2016
March 31, 2016
April 28, 2016
May 26, 2016
June 30, 2016
20
Nov
FY 2017
July 28, 2016
August 25, 2016 (Cancelled)
September 29, 2016
October 27, 2016
November 30, 2016 (Combined with December)
December 15, 2016
January 26, 2017
February 23, 2017
March 30, 2017
April 27, 2017
May 25, 2017
June 29, 2017
20
Nov
FY 2018
July 27, 2017
August 31, 2017 (Cancelled)
September 28, 2017
October 26, 2017
November 30, 2017 (Cancelled)
December 14, 2017
January 25, 2018
February 22, 2018
March 29, 2018
April 26, 2018
May 31, 2018
June 28, 2018 (Cancelled)
20
Nov
FY 2019
July 26, 2018
August 30, 2018
September 27, 2018
October, 2018 – Cancelled
November 1, 2018
December 13, 2018
January 31, 2019
February 28, 2019
March 28, 2019
April 25, 2019
May 30, 2019
June 27, 2019
20
Nov
FY 2020
July 25, 2019
August 29, 2019 (cancelled)
September 26, 2019
October 31, 2019
November, 2019 (combined w/December)
December 12, 2019
January 30, 2020
February 27, 2020
March 12, 2020
March 26, 2020 (special meeting)
April 30, 2020
May 28, 2020
June 25, 2020
11
May
FY 2021
July 30, 2020
August 27, 2020
September 24, 2020
October 29, 2020
November 24, 2020
December 10, 2020
January 28, 2021
February 25, 2021
March 25, 2021
April 29, 2021
May 27, 2021
June 24, 2021
7
Mar
US 95: Rifle Range Road to Wellton-Mohawk Canal Bridge
OVERVIEW
The Arizona Department of Transportation (ADOT), the Federal Highway Administration, and the U.S. Department of Defense are working to improve safety and traffic flow on US 95 between Rifle Range Road (milepost 35) and the Wellton-Mohawk Canal bridge (milepost 39).
PROJECT ELEMENTS
- Crews will reconstruct and widen the existing two-lane roadway into a five-lane roadway while also replacing the bridge over the Wellton-Mohawk Canal.
- Additional work includes roadway excavation, drainage improvements, removing and replacing the pavement and applying new pavement markings.
PROJECT SCHEDULE
- Phase 1 was completed in fall 2022. Crews reconstructed and widened 3.6 miles of roadway between Avenue 9E and Fortuna Wash.
- Phase 2 includes: Widening of 2.96 miles of road between Rifle Range Road (milepost 35) and the Wellton-Mohawk Canal bridge (milepost 39).
- Construction is expected to begin early spring 2023 with completion expected in summer 2024.
WHAT TO EXPECT
- • Delays and lane restrictions on US 95 are expected. Work is scheduled to occur between 6
a.m. to 6 p.m. weekdays. - ADOT will provide advance notice of restrictions and closures to email subscribers and on the project traffic alert web page.
STAY INFORMED
Schedules are subject to change based on weather and other unforeseen factors. Visit the project website at: azdot.gov/projects/southwest-district-projects/us-95-corridor-widening-and-reconstruction for more information and to subscribe for project updates by email or call the ADOT Bilingual Project Information Line at 855.712.8530. For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at AZ511.gov, follow ADOT on Twitter @ArizonaDOT or call 511, except while driving.